Milestones

Fall 2016

Start of construction

Early Spring 2017

Vertical construction begins

Early Summer 2017

Steel structure completed

Summer 2017

Skylights/roof completed

Fall 2017

Building shell completed/interior finish work begins

Late Fall 2017

Permanent power goes online/interior finish work continues

Early Summer 2018

Library, food court, cafes built out (Starbucks, Chick-fil-A, Qdoba)

Late Summer 2018

Construction completed